Force Majeure Clauses in Singapore Contracts: What They Cover and How the Courts Read Them
By Adrian Teo · DL Law Corporation · Advocate & Solicitor of the Supreme Court of Singapore
In Singapore, force majeure exists only as a contract term. If your contract has a force majeure clause, that clause decides which events excuse performance, what you must do when one happens and what relief you get. If it has no such clause, the fallback is the much narrower doctrine of frustration.
So the wording matters. Singapore’s Court of Appeal reads force majeure clauses closely, and the party relying on one has to prove it applies.
This is general information, not legal advice. Whether a particular clause protects you depends on its exact wording, the rest of the contract and the facts.
What Is a Force Majeure Clause?
A force majeure clause relieves one or both parties from performing, usually for a period, when a specified kind of event occurs. In RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd [2007] SGCA 39, the Court of Appeal said its principal purpose is to allocate the risk of future events between the parties, in circumstances “all of which are stipulated within the clause itself”.
Most clauses have 4 working parts:
- The events: a list such as natural disasters, epidemics, war, strikes, government action and failure of supply, often with a catch-all such as “any other cause beyond the party’s reasonable control”.
- The trigger: the effect the event must have, for example that it “prevents”, “hinders” or “delays” performance.
- The process: usually notice within a set time and steps to limit the impact.
- The relief: suspension, an extension of time, or a right to terminate if the event lasts too long.
Is There Force Majeure in Singapore If the Contract Says Nothing?
No. Because force majeure comes from the contract, there is no force majeure relief to claim if the contract does not provide for it. In the words of the Court of Appeal in RDC Concrete, “the precise construction of the clause is paramount as it would define the precise scope and ambit of the clause itself”, and the court gives full effect to what the parties agreed.
Where there is no clause, or the event falls outside it, the question becomes whether the contract has been frustrated. The Court explained in RDC Concrete that where a frustrating event lies beyond a force majeure clause that does not exclude frustration, the consequences of frustration at common law and under the Frustrated Contracts Act 1959 follow instead. Frustration is a far harder test to meet.
How Do Singapore Courts Read a Force Majeure Clause?
Closely, and on the clause’s own words. The Court of Appeal noted in RDC Concrete that the case law suggests courts will construe force majeure clauses strictly. In Holcim (Singapore) Pte Ltd v Precise Development Pte Ltd [2011] SGCA 1, a dispute arising from the 2007 Indonesian sand ban, it held that the party relying on the clause bears the burden of proving that it applies.
“Prevented” is a higher bar than “hindered”
In Holcim, the Court of Appeal agreed that “prevented” connotes a much higher degree of obstacle than “hindered”. The clause in that case used “disrupted”, which the Court treated like “hindered”: neither requires performance to be impossible. If events make continued performance commercially impractical, even though literal performance is still possible, there would generally be a disruption or hindrance.
Performance becoming more expensive is not enough on its own
The Court of Appeal in Holcim held that an increase in costs alone will not constitute a “disruption”, while leaving open the position where an increase is astronomical. What carried the day was a genuine shortage of sand caused by the ban, not the higher price.
“Beyond your control” brings a duty to take reasonable steps
Where a clause covers only events beyond the affected party’s control, that party must take reasonable steps to avoid the event or its effects. The Court in Holcim reasoned that if you did not take reasonable steps, the event cannot be said to have been beyond your control. The duty is to take reasonable steps, not every possible step, and whether you did so is a question of fact. Without “beyond control” wording, whether a similar duty exists depends on the language of the clause.
The supplier in Holcim succeeded. It had told the customer that only main contractors could draw sand from the government stockpile, and offered to credit back the cost of any sand the customer supplied. The customer did not respond. The Court of Appeal held that the supplier had taken reasonable steps and the clause applied.
What Should You Do When a Force Majeure Event Happens?
Start from the clause. These steps are practical ones; your clause sets the actual requirements.
- Read the clause first. Check whether the event is listed or within the catch-all, which trigger word is used, and what relief is available.
- Give notice exactly as the clause requires. Note any deadline, the required form and the address for notices, and treat each requirement as strict.
- Keep the notice factual. Describe the event, the obligations affected and the steps you are taking, without conceding more than the facts show.
- Take reasonable steps, and record them. Look for alternative sources or methods, and ask the other party for help where it has access you lack. Holcim was decided on letters showing what the supplier had tried.
- Keep performing what you can, and watch for the end of the event. Relief is often temporary: in RDC Concrete, the clause suspended or limited the contract “until such circumstance ceases”.
If you receive a force majeure notice, test it against the same clause: is the event covered, has it had the effect the trigger word requires, what steps has the other side taken, and was notice given in time? Reply in writing and reserve your rights.
Force Majeure or Frustration: What Is the Difference?
Frustration does not depend on any clause, but it applies only in exceptional cases. In Alliance Concrete Singapore Pte Ltd v Sato Kogyo (S) Pte Ltd [2014] SGCA 35, the Court of Appeal said frustration discharges both parties automatically, by operation of law, where a supervening event, without the default of either party, renders a contractual obligation radically or fundamentally different from what was agreed. A mere increase in cost will not frustrate a contract, although an astronomical one might.
| Question | Force majeure clause | Frustration |
|---|---|---|
| Where it comes from | The contract | The common law, with consequences under the Frustrated Contracts Act 1959 |
| What triggers it | The events and trigger words in the clause | An event, without either party’s fault, that makes the obligation radically different |
| What happens | Whatever the clause provides: suspension, extension or termination | The contract ends automatically for both parties |
When a contract is frustrated, section 2 of the Frustrated Contracts Act 1959 makes sums paid before discharge recoverable and sums still payable cease to be payable. The court may let the recipient keep some or all of the money, up to the expenses it incurred in performing, and a party who obtained a valuable benefit may have to pay a just sum for it. Under section 3(3), a contractual provision intended to apply in circumstances that would frustrate the contract takes priority. Section 3(5) excludes some contracts from the Act, including contracts of insurance, charterparties other than time or demise charterparties, and other contracts for the carriage of goods by sea.
A force majeure clause can be drafted to exclude frustration, but the Court of Appeal in RDC Concrete said it must do so in clear and unambiguous terms.
What Happened to the COVID-19 Contract Relief?
It has expired. Part 2 of the COVID-19 (Temporary Measures) Act 2020 gave temporary relief to a party to certain categories of contract who was unable to perform an obligation because, to a material extent, of a COVID-19 event. Once that party served a notification for relief, section 5 stopped the other side, for a prescribed period, from steps such as starting court or arbitration proceedings or enforcing security over immovable property.
Under section 1(2A), Part 2 remained in force only until the end of 19 April 2022. Unless Parliament legislates again, a business hit by a future epidemic will have to rely on its force majeure clause or on frustration, which is a good reason to check the clause now.
How Should a Business Draft a Force Majeure Clause?
Write it for the disruptions your business is actually exposed to. A commercial lawyer reviewing a supply, services or lease agreement would usually check these points:
- Name the events that matter to you, such as epidemics, government restrictions, export bans, failure of a named supplier or cyber incidents. A catch-all helps but does not replace naming them.
- Choose the trigger word deliberately. “Prevented” protects only when performance is blocked; “hindered” sets a lower bar, as Holcim shows.
- Decide about price rises. If you want relief for extreme price movements, say so, or use a separate price adjustment clause.
- Set the notice rules: deadline, form, content, recipient, and the effect of late notice.
- Spell out mitigation, including whether the other party must cooperate.
- Define the relief, including a right to terminate if the event lasts beyond a fixed number of days, and say whether payment obligations are suspended.
- Address frustration in clear words if the clause is meant to apply even to events that would otherwise frustrate the contract.
Read the clause alongside the rest of the risk allocation, in particular any indemnity clause and the limitation of liability. Our guide to contract lawyers in Singapore explains what a contract review usually covers.
Frequently asked questions
What does force majeure mean in a contract?
It is a clause that relieves a party from performing, usually for a time, when a specified event occurs, typically one outside its control. In Singapore it exists only if the contract provides for it, and the Court of Appeal has said the precise construction of the clause is paramount.
Is COVID-19 a force majeure event in Singapore?
Only if your clause covers it, for example through words such as “epidemic”, “pandemic” or “government action”, and its trigger is met. The statutory relief under Part 2 of the COVID-19 (Temporary Measures) Act 2020 ended at the end of 19 April 2022.
Can I rely on force majeure because my costs have gone up?
Generally not on that ground alone. In Holcim, the Court of Appeal held that an increase in costs by itself does not amount to a disruption under a force majeure clause. A real shortage or inability to perform is different, if the clause covers it.
Speak with our corporate team
We review and draft commercial contracts for Singapore businesses, including the force majeure, indemnity and limitation of liability clauses that decide who carries the risk. Read more about our corporate and SME practice. If an event is already affecting your contract, send us the contract and the correspondence so far, and we will review what the clause requires of you and what notice to give.
Call (65) 6557 0215 or email contactus@dllclegal.com. We typically respond within minutes during business hours.
This article is general information about force majeure clauses in Singapore contracts and is not legal advice. The effect of any clause depends on its exact wording and the facts, and the law develops through new decisions, so confirm the current position on Singapore Statutes Online or with a lawyer before acting. For advice on your specific matter, consult an Advocate & Solicitor.
Statutory and case references: Frustrated Contracts Act 1959, sections 2 and 3; COVID-19 (Temporary Measures) Act 2020, sections 1(2A) and 5; RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd [2007] SGCA 39; Holcim (Singapore) Pte Ltd v Precise Development Pte Ltd [2011] SGCA 1; Alliance Concrete Singapore Pte Ltd v Sato Kogyo (S) Pte Ltd [2014] SGCA 35.