Email: contactus@dllclegal.com 

Liquidated Damages in Singapore: When the Clause Holds and When It Is a Penalty

Liquidated Damages in Singapore: When the Clause Holds and When It Is a Penalty

Liquidated Damages in Singapore: When the Clause Holds and When It Is a Penalty

This is general information, not legal advice. Whether a particular clause can be enforced depends on its wording and on the circumstances when the contract was made.

Liquidated damages are a sum or formula, agreed in advance, that one party pays if it breaches the contract. A Singapore court enforces the clause if the sum was a genuine pre-estimate of the likely loss when the contract was made. If the sum was extravagant compared with that loss, the clause is a penalty and is not enforced.

The same test applies to an owner charging a daily sum for late handover and to a supplier facing a late-delivery claim.

What Are Liquidated Damages in Singapore Law?

A liquidated damages clause fixes the sum payable for a particular breach. It is often a rate per day or per week, or a formula. “Liquidated” means the amount is fixed, or can be worked out from the contract. The Court of Appeal calls these “LD clauses”.

The Court of Appeal explained the structure in Denka Advantech Pte Ltd v Seraya Energy Pte Ltd [2020] SGCA 119. A contract contains primary obligations, such as the promise to finish works by a stated date. A liquidated damages clause is a secondary obligation. It is the duty to pay compensation when a primary obligation is broken.

The heading on the clause does not settle what it is. The Court of Appeal noted that the words parties use are “indicative but inconclusive”. A clause headed “liquidated damages” can still be a penalty.

What Is the Difference Between Damages and Liquidated Damages?

The court assesses general damages, also called unliquidated damages, after a breach. It looks at the loss the innocent party actually suffered. Nobody knows the figure until the court decides it.

Liquidated damages are agreed before any breach. If the clause is valid, the innocent party claims the agreed sum. In Denka, the Court of Appeal upheld the clauses. It then found it unnecessary to decide what common law damages would have been.

The court will not strike down a valid clause just because it might pay more than the actual loss in some situations. On this point, the Court of Appeal quoted with approval the Privy Council in Philips Hong Kong. What matters is whether the sum was extravagant against the range of losses expected at signing.

Liquidated damages are one remedy among several. Our guide to breach of contract in Singapore covers the others, including termination.

What Are Examples of Liquidated Damages?

  • Late completion of construction or fit-out works. A sum for each day or week that handover runs past the completion date. The owner’s likely losses guide the rate, such as rent on a temporary site or lost trading days.
  • Late delivery under a supply contract. A sum for each day a delivery is late. It is often a percentage of the value of the late goods, with an overall limit.
  • Early termination of a long-term contract. Denka concerned electricity retail agreements. When the customer walked away, a formula applied: 40% of its average recent monthly bill, multiplied by the months left. The Court of Appeal held these clauses were not penalties.

The Court of Appeal also referred to an older House of Lords case, Lord Elphinstone v Monkland Iron and Coal Co. A company that failed to restore land on time owed a fixed sum per acre left unrestored. The House of Lords held that this was liquidated damages, not a penalty.

When Is a Liquidated Damages Clause an Unenforceable Penalty?

The test is whether the clause was a genuine pre-estimate of the likely loss at the time of contracting. If the sum goes beyond compensation, it is a penalty clause.

The court applies the guides Lord Dunedin set out in Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79. The Court of Appeal restated them in Denka:

  1. Extravagance. A sum that is extravagant and unconscionable against the greatest loss that could conceivably follow is penal.
  2. Late payment of money. Where the only breach is failing to pay money, a clause demanding a larger sum is penal.
  3. One sum for many breaches. A single lump sum for breaches of varying seriousness is presumed to be a penalty. The presumption can be rebutted.
  4. Hard-to-measure loss. A clause is not a penalty just because the loss was almost impossible to estimate precisely.

The Court of Appeal said the greatest loss test is of overarching importance. If the sum is not extravagant against the greatest possible loss, the clause should be treated as a genuine pre-estimate. A single lump sum only raises a presumption.

The judgment adds 3 further points:

  • The test looks back to signing. The court asks what loss was reasonably anticipated when the contract was made. It avoids hindsight.
  • Context counts. Bargaining power and the purpose of the contract are relevant. The court said the rule should be used sparingly, to respect freedom of contract.
  • The challenger carried the burden. In Denka, the customer said the clause was a penalty. It had to prove the 40% multiplier was not a genuine pre-estimate.

Does Singapore Follow the UK Cavendish v Makdessi Approach?

No. In Cavendish Square Holding BV v Makdessi [2016] AC 1172, the UK Supreme Court took a wider view. A clause could be valid if it protected a “legitimate interest” of the innocent party. That interest could go beyond compensation.

In Denka, the Court of Appeal declined to follow Cavendish and endorsed the Dunlop principles. It reasoned that a sum payable on breach above the pre-estimate of likely loss is penal by nature. That is so even if the clause served the claimant’s commercial interests. The only “legitimate interest” the penalty rule recognises is compensation.

So in Singapore, a clause designed to deter breach, rather than compensate for it, is exposed. A sound business reason for a high figure will not save it. If your template was drafted with English law in mind, check its figures against the Singapore test.

Does the Penalty Rule Apply Only to a Breach of Contract?

Yes. The Court of Appeal held that the penalty rule applies only where there is a breach of contract. It declined to follow the High Court of Australia, which had extended the rule beyond breach.

This matters for payments triggered by events that are not breaches. One example is a right to end the contract early by notice, with a set payment due on exit. The Court of Appeal treated such a payment as the agreed term for using that right. The penalty rule does not test it. Other doctrines, such as the narrow doctrine of unconscionability, may still apply.

Some clauses work both ways. In Denka, one agreement required a payment if the contract ended “for any reason whatsoever”. The Court of Appeal called this a “hybrid” obligation. Where termination followed a breach, the penalty rule applied. A lawful termination by notice would not have engaged it.

What Happens If a Clause Is a Penalty?

The court will not enforce it. In Denka, the Court of Appeal said it would adopt the UK approach. The penal clause is void, and the parties are left to the remedies under the general law. The court noted the point had not been argued, and left room to reconsider it.

The innocent party then claims general damages, and the court assesses the actual loss. Keep records of your real losses from the start, even with a liquidated damages clause in place.

How Should a Business Draft or Review a Liquidated Damages Clause?

The Dunlop guides translate into drafting steps. A commercial lawyer can test your figures against them before the contract is signed.

  1. Record how you reached the figure. Note the losses you expected and how you estimated them. In Denka, evidence of estimated losses showed the 40% multiplier sat within the range, toward its lower end.
  2. Scale the sum to the breach. A rate per day of delay tracks the loss. In Denka, the formula shrank as fewer months remained. That helped show it was not an indiscriminate lump sum.
  3. Avoid one figure for every breach. One sum for any breach, large or small, raises the presumption of a penalty.
  4. Take care with late payment clauses. Demanding a larger sum only because money was paid late falls within the second Dunlop guide.
  5. State the limits. Set a maximum, and say whether the clause is the only remedy for delay.
  6. Deal with delay the other side causes. Set out how extensions of time are claimed and who decides them.
  7. Check the triggers. Decide whether each payment arises on breach, on termination by notice, or both.

If you are the party signing, ask how the figure was reached. Compare it with the contract value and the losses the other side could realistically suffer. A corporate lawyer can flag a clause likely to be challenged. Liquidated damages often sit near an indemnity in the same contract. Our guide to indemnity clauses in Singapore covers that clause.

Frequently asked questions

Are liquidated damages enforceable in Singapore?

Yes, if the sum was a genuine pre-estimate of the likely loss when the contract was made. The Court of Appeal confirmed this test in Denka. A sum that is extravagant against the greatest likely loss is a penalty.

Is a penalty clause illegal in Singapore?

It is not a crime to include one, but the court will not enforce it. The Court of Appeal indicated that a penal clause is void. The innocent party can still claim ordinary damages for its actual loss.

Do I need to prove my actual loss to claim liquidated damages?

If the clause is valid, the claim is for the agreed sum. In Denka, the court did not assess common law damages once it upheld the clauses. Keep records of your actual loss anyway, in case the clause is challenged.

Does the penalty rule apply if the contract ends without a breach?

No. In Singapore the rule applies only to sums payable on a breach of contract. A payment due on a lawful termination by notice is not tested under it. Other doctrines may still apply.

Speak with our corporate team

We draft and review commercial contracts, including liquidated damages clauses. We also advise businesses facing a claim under one. If a delay clause is being enforced against you, send us the contract and the correspondence. We will tell you where the clause stands.

Call (65) 6557 0215 or email contactus@dllclegal.com. We typically respond within minutes during business hours.


This article is general information about liquidated damages and penalty clauses in Singapore and is not legal advice. Whether a clause is enforceable depends on its wording and the facts. The law develops through new decisions, so confirm the current position with the Singapore Courts or a lawyer before acting. For advice on your specific matter, consult an Advocate & Solicitor.

Case references: Denka Advantech Pte Ltd v Seraya Energy Pte Ltd [2020] SGCA 119, [2021] 1 SLR 631, paragraphs 65–66, 99, 151–152, 173–174, 184–185, 247, 281, 287, 293 and 305–310; Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79; Cavendish Square Holding BV v Makdessi [2016] AC 1172; Lord Elphinstone v Monkland Iron and Coal Co Ltd (1886) 11 App Cas 332; Philips Hong Kong Ltd v Attorney-General of Hong Kong [1993] 1 LRC 775 (Privy Council).

Sertai Komuniti Kami

Got a question for us?

Table of Contents

Scroll to Top

Get Your Free DLLC Legal Handbook

Enter your email to access the download instantly.